A network diagram turns a messy project into a plan you can test. Find the critical path, then read the float, and you know which delays matter.
How do I find the critical path and float, and what do I write once I have the numbers?
Project management plans and controls a one-off job with a start, an end and a budget. Network analysis maps the activities in order, finds the critical path (the longest route, with zero float) and calculates float: latest finish time minus duration minus earliest start time. It shows managers where delay matters and where it does not.
Year 12 (7137/7138): This is AS content (AS is the first-year qualification), so it is examined from 2027 on AS Paper 2 and from 2028 on A-level Paper 2. Learn the formula, practise drawing and reading networks, and always finish with a judgement.
Year 13 (7132, June 2027): Your exam is on the outgoing specification, and I cannot place this topic confidently in a 7132 section. Check your teacher's scheme first. The skills still help: planning, timing and judging risk appear in many operations and change questions.
A project is a one-off piece of work with a start, an end, a budget and a clear outcome. Opening a new shop, launching a product or building a railway are all projects. Project management is the planning, organising and controlling of that work so it finishes on time, on budget and to the right quality.
Network analysis is the tool. It draws each activity as a box, links the boxes in the order they must happen, and adds durations. From that you can find the shortest possible project time and the activities that cannot slip.
You find EST by working forwards from the start. At a merge point, take the larger finish time, because every route into it must be complete. You find LFT by working backwards from the end. At a split, take the smaller start time, because the earliest-needed route sets the deadline.
The value is practical. Managers can put their best people and tightest checks on critical activities, and use float to move resources elsewhere. They can also see how a delay or a cost-saving change affects the finish date.
Network analysis is a sophisticated concept in Annex 8 of the specification. That means it is credited when you use it accurately, so use the correct terms and numbers.
Illustrative figures: a café refit has six activities. A is design (3 weeks). B is ordering equipment (2 weeks, after A). C is strip-out (4 weeks, after A). D is installation (3 weeks, after B and C). E is staff training (5 weeks, after A). F is opening (1 week, after D and E). Figure 1 shows the network.
| Activity | Duration | After | EST | LFT | Float |
|---|---|---|---|---|---|
| A | 3 | – | 0 | 3 | 0 |
| B | 2 | A | 3 | 7 | 7 − 2 − 3 = 2 |
| C | 4 | A | 3 | 7 | 7 − 4 − 3 = 0 |
| D | 3 | B, C | 7 | 10 | 10 − 3 − 7 = 0 |
| E | 5 | A | 3 | 10 | 10 − 5 − 3 = 2 |
| F | 1 | D, E | 10 | 11 | 11 − 1 − 10 = 0 |
D starts at week 7, not week 5, because it must wait for C (3 + 4 = 7). F starts at week 10 because D finishes at week 10 but E finishes at week 8. The critical path is A, C, D, F, which takes 3 + 4 + 3 + 1 = 11 weeks.
So the critical path is not fixed. It can change when durations change, and a good answer says so.
Big projects show why dependencies matter. When a late activity sits on the critical path, the whole finish date moves, and costs rise with every extra month of running the site and paying contractors.
The Elizabeth line is the east-west railway across London, built as Crossrail. It opened on 24 May 2022, three and a half years late and more than £4 billion over budget, at a total cost of £18.8 billion.[1]
EDF, the French state-owned energy firm, is building Hinkley Point C, a nuclear power station in Somerset. In January 2024 it raised its cost estimate to between £31 billion and £34 billion in 2015 prices, up from £25 billion to £26 billion, and the opening slipped into the 2030s.[2]
HS2 (High Speed 2) is a high-speed railway being built from London to Birmingham. In 2025 its chief executive Mark Wild blamed slow progress partly on weak design maturity and consenting, and the Transport Secretary confirmed services would not start by 2033.[3] In network terms, starting activities before earlier ones are settled makes durations unreliable, so the critical path is harder to trust. That link is my own reading, not a claim from the source.
Network analysis is only as good as its inputs. Durations are estimates, so a small error on a critical activity moves the whole project. This is why Hinkley Point C-style overruns can appear even in a well-drawn plan.
A strong judgement says which factor matters most in the case, why, and what the manager should do. For example: crash the critical path only if the extra cost is smaller than the revenue gained from opening earlier.
Every AQA Business question uses one of five command words, each with a fixed mark tariff, and quantitative questions sit inside the 9 and 15-mark formats. The A-level papers have no 2 or 4-mark questions. Open each format to see how this topic appears in it. All questions here are original Curriculum Circle practice questions, not board questions.
On this topicYou are asked for a precise meaning, such as critical path or float time. Give the term plus what makes it distinct.
What earns the marksAO1 only: two marks for accurate knowledge, usually one for the idea and one for the detail.
CC practice questionDefine 'float time'. (2 marks)
On this topicYou give a reason or effect and tie it to the business in the case, for example why float helps a manager.
What earns the marksAO1 for the idea and AO2 for applying it to the named firm.
CC practice questionExplain one way a bakery manager could use float time when fitting out a new shop. (4 marks)
On this topicYou build a chain of reasoning from a network fact, such as a delay to a critical activity, to a consequence for cost or the launch date.
What earns the marksAO1 and AO2 plus AO3: a developed chain linked with because and so.
CC practice questionAnalyse how a two-week delay to a critical activity could affect a firm launching a new product. (6 marks)
On this topicYou weigh the case for and against using network analysis, or for and against shortening the critical path, then give a judgement.
What earns the marksAO1 to AO3 for the two sides and AO4 for a judgement that depends on the case evidence.
CC practice questionAssess the value of network analysis to a company building a new factory. (9 marks)
On this topicYou compare two courses of action, such as paying to cut the critical path or keeping the plan, then recommend one with justification.
What earns the marksAll four AOs: knowledge, application, analysis, and a justified recommendation that considers cost, time and risk.
CC practice questionEvaluate whether a hotel chain should pay for extra workers to finish a refurbishment earlier or keep to the original schedule. (15 marks)
On this topicThe case gives activities, durations and dependencies. You find EST, LFT, float and the critical path, then use them in a judgement.
What earns the marksAO1 and AO3 for accurate calculation, and AO4 when you interpret the numbers for a decision.
CC practice questionUsing the table of activities in the case study, calculate the float time for activity E and the length of the critical path. Assess whether the manager should move staff from E to the critical path. (9 marks)
| Weight | What it is | What it means on project management and network analysis | |
|---|---|---|---|
| AO1 | 32.5% AS · 24.44% A-level | Knowledge and understanding of terms, concepts, theories, methods and models | State the formula correctly and define terms such as critical path and float time. Show correct forward and backward passes. |
| AO2 | 27.5% AS · 24.44% A-level | Application to the business context in the case study | Use the case's actual activities, durations and deadline. Name the critical activity and the date at risk. |
| AO3 | 20% AS · 26.66% A-level | Analysis of issues and their impact on individuals and organisations | Build chains such as: the activity is critical, so delay moves the finish date, so costs and customer trust suffer. |
| AO4 | 20% AS · 24.44% A-level | Evaluation of quantitative and qualitative information to make judgements | Weigh cost against time, judge reliability of the estimates, and make a recommendation the numbers support. |
Weightings are approximate and taken from the AQA AS 7137 and A-level 7138 specification [0].
Evaluate whether Orchard Bakery should pay for extra workers to shorten the critical path of its new-shop project, or keep to the planned 11 weeks and use spare float to control costs. (15 marks)
The critical path is A, C, D, F, so any saving on C shortens the whole project, because every route into D waits for C. Paying overtime to cut C by one week would bring opening forward to week 10, so the bakery earns a week of sales sooner. The saving stops after C falls to 2 weeks, because all routes are then critical and the 9-week limit is set by the others. Keeping to 11 weeks lets B and E, with 2 weeks of float each, use cheaper, slower resources, so costs fall.
The recommendation depends on what one extra week of trading is worth against the overtime bill. If the shop would open before a busy season, crashing C is justified, because the revenue gained is larger than the extra pay. If the date is not tied to an event, the saving may not cover the cost, so keeping the plan is wiser. The estimates also matter: if C is uncertain, spending to shorten it may be wasted. I would recommend shortening C by one week only, and monitoring E, because its 2 weeks of float could vanish if training overruns.
The Elizabeth line, London's east-west railway built as Crossrail, opened on 24 May 2022. Reuters-style reporting said it opened three and a half years late and more than £4 billion over budget, at a total cost of £18.8 billion.[1]
In January 2024 EDF raised its Hinkley Point C cost estimate to between £31 billion and £34 billion in 2015 prices, up from £25 billion to £26 billion. Its opening slipped into the 2030s.[2]
In 2025 HS2's chief executive Mark Wild said progress in the first two years of main works was too slow, citing weak design maturity and consenting. The Transport Secretary confirmed that HS2 services would not start by 2033.[3]
Everything above is the topic page. The pieces below take it further. Each one trains a particular assessment objective rather than covering the topic again, and they are added over the year.
Figures and facts were checked against these sources on 2 November 2026. Worked numbers labelled "Illustrative figures" are invented for teaching.
The CC Business revision platform has timed network questions with Criterion Marking Engine feedback, and the Inner Academy's recorded lessons walk through forward and backward passes.
See the Business platformThe Inner Academy