A-Level Business/Year 12 · 3.2.2 Operations management/Project management and network analysis
Topic page · AS Paper 2 · A-level Paper 2 (also used in Paper 3 strategy cases)

Project management and network analysis

A network diagram turns a messy project into a plan you can test. Find the critical path, then read the float, and you know which delays matter.

How do I find the critical path and float, and what do I write once I have the numbers?

Spec pointAQA 3.2.2
YearYear 12 (AS and A-level)
PapersAS Paper 2 · A-level Paper 2 (also used in Paper 3 strategy cases)
ModelNetwork analysis (critical path) and the float time formula
Typical marks2 to 15
Where this sits on your specification
AQA AS Business 7137
3.2.2
Operations management · Year 12
AQA A-level Business 7138
3.2.2
Operations management · Paper 2
Outgoing A-level 7132 (exams June 2027)
New in 7138 as a named, assessed topic. I am not confident it sits in a specific 7132 section, so check your teacher's scheme.
New in 7138 as a named, assessed topic. I am not confident it sits in a specific 7132 section, so check your teacher's scheme.
Short answer

Project management plans and controls a one-off job with a start, an end and a budget. Network analysis maps the activities in order, finds the critical path (the longest route, with zero float) and calculates float: latest finish time minus duration minus earliest start time. It shows managers where delay matters and where it does not.

Year 12 or Year 13?

Year 12 (7137/7138): This is AS content (AS is the first-year qualification), so it is examined from 2027 on AS Paper 2 and from 2028 on A-level Paper 2. Learn the formula, practise drawing and reading networks, and always finish with a judgement.

Year 13 (7132, June 2027): Your exam is on the outgoing specification, and I cannot place this topic confidently in a 7132 section. Check your teacher's scheme first. The skills still help: planning, timing and judging risk appear in many operations and change questions.

Section IWhat a project is and why networks helpThe purpose of project management and the vocabulary of network analysis.

A project is a one-off piece of work with a start, an end, a budget and a clear outcome. Opening a new shop, launching a product or building a railway are all projects. Project management is the planning, organising and controlling of that work so it finishes on time, on budget and to the right quality.

Network analysis is the tool. It draws each activity as a box, links the boxes in the order they must happen, and adds durations. From that you can find the shortest possible project time and the activities that cannot slip.

The language you must use

  • Activity and duration: a task and the time it takes (days or weeks).
  • Dependency: an activity that cannot start until another has finished.
  • Earliest start time (EST): the soonest an activity can begin, once everything before it is done.
  • Latest finish time (LFT): the latest an activity can end without delaying the whole project.
  • Critical path: the longest route through the network. It sets the minimum project time.
  • Float time: the spare time an activity has. Critical activities have zero float.

You find EST by working forwards from the start. At a merge point, take the larger finish time, because every route into it must be complete. You find LFT by working backwards from the end. At a split, take the smaller start time, because the earliest-needed route sets the deadline.

The value is practical. Managers can put their best people and tightest checks on critical activities, and use float to move resources elsewhere. They can also see how a delay or a cost-saving change affects the finish date.

Network analysis is a sophisticated concept in Annex 8 of the specification. That means it is credited when you use it accurately, so use the correct terms and numbers.

Section IICalculating float and amending a networkWorked example: forward pass, backward pass, float, and what changes when durations change.
Float time = latest finish time − duration of activity − earliest start timeFloat of zero means the activity is critical. The project time is the largest earliest finish time.

Illustrative figures: a café refit has six activities. A is design (3 weeks). B is ordering equipment (2 weeks, after A). C is strip-out (4 weeks, after A). D is installation (3 weeks, after B and C). E is staff training (5 weeks, after A). F is opening (1 week, after D and E). Figure 1 shows the network.

ActivityDurationAfterESTLFTFloat
A3–030
B2A377 − 2 − 3 = 2
C4A377 − 4 − 3 = 0
D3B, C71010 − 3 − 7 = 0
E5A31010 − 5 − 3 = 2
F1D, E101111 − 1 − 10 = 0

D starts at week 7, not week 5, because it must wait for C (3 + 4 = 7). F starts at week 10 because D finishes at week 10 but E finishes at week 8. The critical path is A, C, D, F, which takes 3 + 4 + 3 + 1 = 11 weeks.

Amending the network

  • Speed up a critical activity. If C takes 3 weeks, the project takes 10 weeks. B and E now have 1 week of float each.
  • Keep shortening C. At 2 weeks, every route is 9 weeks, so all activities are critical. Shortening C further saves nothing, because the other routes still take 9 weeks.
  • Delay a non-critical activity. If E takes 8 weeks, that is 3 weeks against 2 weeks of float. The project takes 12 weeks and A, E, F becomes the critical path.

So the critical path is not fixed. It can change when durations change, and a good answer says so.

Café refit: activity-on-node network (weeks)A 3 wksfloat 0B 2 wksfloat 2C 4 wksfloat 0E 5 wksfloat 2D 3 wksfloat 0F 1 wkfloat 0Solid = critical path. Dashed = has float.Critical path A, C, D, F = 11 weeks
Figure 1. Illustrative figures. Work runs left to right. The solid line A, C, D, F is the critical path at 11 weeks. B and E each have 2 weeks of float.
Section IIIHow real projects show the same logicLarge UK projects and what delay on dependent activities does to cost and time.

Big projects show why dependencies matter. When a late activity sits on the critical path, the whole finish date moves, and costs rise with every extra month of running the site and paying contractors.

The Elizabeth line is the east-west railway across London, built as Crossrail. It opened on 24 May 2022, three and a half years late and more than £4 billion over budget, at a total cost of £18.8 billion.[1]

EDF, the French state-owned energy firm, is building Hinkley Point C, a nuclear power station in Somerset. In January 2024 it raised its cost estimate to between £31 billion and £34 billion in 2015 prices, up from £25 billion to £26 billion, and the opening slipped into the 2030s.[2]

HS2 (High Speed 2) is a high-speed railway being built from London to Birmingham. In 2025 its chief executive Mark Wild blamed slow progress partly on weak design maturity and consenting, and the Transport Secretary confirmed services would not start by 2033.[3] In network terms, starting activities before earlier ones are settled makes durations unreliable, so the critical path is harder to trust. That link is my own reading, not a claim from the source.

Section IVEvaluation: what network analysis depends onWhen the tool helps, when it misleads, and how to reach a judgement.

Network analysis is only as good as its inputs. Durations are estimates, so a small error on a critical activity moves the whole project. This is why Hinkley Point C-style overruns can appear even in a well-drawn plan.

  • Size and complexity: the bigger the project, the more value a network gives, because the dependencies are too many to hold in your head. For a two-day job it adds cost without benefit.
  • Quality of estimates: experience of similar projects makes durations reliable. A first-of-a-kind project makes them uncertain, so build in float and review often.
  • Trade-offs: shortening the critical path usually costs more, for example overtime or extra contractors. The saving only pays if finishing earlier earns more than it costs, such as opening before a peak season.
  • Quality and people: rushing critical activities can harm quality and staff morale. A network shows time, not quality.
  • Time horizon: a plan needs updating as work proceeds, because the critical path can change.

A strong judgement says which factor matters most in the case, why, and what the manager should do. For example: crash the critical path only if the extra cost is smaller than the revenue gained from opening earlier.

Section VMistakes that lose marksThe errors examiners see most often with networks and float.

Watch for these

  • At a merge, taking the smaller finish time instead of the larger one. Every route in must be complete, so take the larger.
  • Mixing up float and duration. Float is spare time, not the length of the task.
  • Writing that a non-critical activity can be delayed without limit. It can slip only by its float, and sharing float between activities can use it up.
  • Stating the critical path and stopping. You must interpret it: what it means for the deadline, cost and risk in the case.
  • Forgetting the network can change when durations change.
Key termsKeywords to use preciselyThe terms examiners expect you to define and use correctly on this topic.
ProjectA one-off piece of work with a start, an end, a budget and a defined outcome.
Network analysisA planning method that maps activities, their order and their durations to find the shortest project time.
Critical pathThe longest route through a network, which sets the minimum time the project can take.
Float timeThe spare time an activity has before it delays the project: latest finish time minus duration minus earliest start time.
Earliest start time (EST)The soonest an activity can begin once all the activities before it are finished.
Latest finish time (LFT)The latest an activity can end without delaying the project's completion.
DependencyA link showing that one activity cannot start until another has finished.
How it is examinedSix question archetypesDefine, Explain, Analyse, Assess, Evaluate and quantitative questions, with the AOs each one rewards.

Every AQA Business question uses one of five command words, each with a fixed mark tariff, and quantitative questions sit inside the 9 and 15-mark formats. The A-level papers have no 2 or 4-mark questions. Open each format to see how this topic appears in it. All questions here are original Curriculum Circle practice questions, not board questions.

ARCHETYPE 01Define2 marks · AS onlyAO1

On this topicYou are asked for a precise meaning, such as critical path or float time. Give the term plus what makes it distinct.

What earns the marksAO1 only: two marks for accurate knowledge, usually one for the idea and one for the detail.

CC practice questionDefine 'float time'. (2 marks)

ARCHETYPE 02Explain4 marks · AS onlyAO1 · AO2

On this topicYou give a reason or effect and tie it to the business in the case, for example why float helps a manager.

What earns the marksAO1 for the idea and AO2 for applying it to the named firm.

CC practice questionExplain one way a bakery manager could use float time when fitting out a new shop. (4 marks)

ARCHETYPE 03Analyse6 marksAO1–AO3

On this topicYou build a chain of reasoning from a network fact, such as a delay to a critical activity, to a consequence for cost or the launch date.

What earns the marksAO1 and AO2 plus AO3: a developed chain linked with because and so.

CC practice questionAnalyse how a two-week delay to a critical activity could affect a firm launching a new product. (6 marks)

ARCHETYPE 04Assess9 marksAO1–AO4

On this topicYou weigh the case for and against using network analysis, or for and against shortening the critical path, then give a judgement.

What earns the marksAO1 to AO3 for the two sides and AO4 for a judgement that depends on the case evidence.

CC practice questionAssess the value of network analysis to a company building a new factory. (9 marks)

ARCHETYPE 05Evaluate15 marksAO1–AO4

On this topicYou compare two courses of action, such as paying to cut the critical path or keeping the plan, then recommend one with justification.

What earns the marksAll four AOs: knowledge, application, analysis, and a justified recommendation that considers cost, time and risk.

CC practice questionEvaluate whether a hotel chain should pay for extra workers to finish a refurbishment earlier or keep to the original schedule. (15 marks)

ARCHETYPE 06Quantitative9 or 15 marksAO1–AO4

On this topicThe case gives activities, durations and dependencies. You find EST, LFT, float and the critical path, then use them in a judgement.

What earns the marksAO1 and AO3 for accurate calculation, and AO4 when you interpret the numbers for a decision.

CC practice questionUsing the table of activities in the case study, calculate the float time for activity E and the length of the critical path. Assess whether the manager should move staff from E to the critical path. (9 marks)

Assessment objectivesWhat the examiner is testingAO1 to AO4, their weightings, and what each one means on this topic.
 WeightWhat it isWhat it means on project management and network analysis
AO132.5% AS · 24.44% A-levelKnowledge and understanding of terms, concepts, theories, methods and modelsState the formula correctly and define terms such as critical path and float time. Show correct forward and backward passes.
AO227.5% AS · 24.44% A-levelApplication to the business context in the case studyUse the case's actual activities, durations and deadline. Name the critical activity and the date at risk.
AO320% AS · 26.66% A-levelAnalysis of issues and their impact on individuals and organisationsBuild chains such as: the activity is critical, so delay moves the finish date, so costs and customer trust suffer.
AO420% AS · 24.44% A-levelEvaluation of quantitative and qualitative information to make judgementsWeigh cost against time, judge reliability of the estimates, and make a recommendation the numbers support.

Weightings are approximate and taken from the AQA AS 7137 and A-level 7138 specification [0].

Exam applicationA model chain of reasoningAnalysis, then evaluation, on an original practice question.

Evaluate whether Orchard Bakery should pay for extra workers to shorten the critical path of its new-shop project, or keep to the planned 11 weeks and use spare float to control costs. (15 marks)

Analysis

The critical path is A, C, D, F, so any saving on C shortens the whole project, because every route into D waits for C. Paying overtime to cut C by one week would bring opening forward to week 10, so the bakery earns a week of sales sooner. The saving stops after C falls to 2 weeks, because all routes are then critical and the 9-week limit is set by the others. Keeping to 11 weeks lets B and E, with 2 weeks of float each, use cheaper, slower resources, so costs fall.

Evaluation

The recommendation depends on what one extra week of trading is worth against the overtime bill. If the shop would open before a busy season, crashing C is justified, because the revenue gained is larger than the extra pay. If the date is not tied to an event, the saving may not cover the cost, so keeping the plan is wiser. The estimates also matter: if C is uncertain, spending to shorten it may be wasted. I would recommend shortening C by one week only, and monitoring E, because its 2 weeks of float could vanish if training overruns.

Why this works

The judgement links the numbers to a decision test: extra revenue from opening earlier against the extra cost, with a limit set by the network.
Real worldWhere you have already seen thisCurrent, dated examples you can use for AO2, each with its source.
01

The Elizabeth line, London's east-west railway built as Crossrail, opened on 24 May 2022. Reuters-style reporting said it opened three and a half years late and more than £4 billion over budget, at a total cost of £18.8 billion.[1]

02

In January 2024 EDF raised its Hinkley Point C cost estimate to between £31 billion and £34 billion in 2015 prices, up from £25 billion to £26 billion. Its opening slipped into the 2030s.[2]

03

In 2025 HS2's chief executive Mark Wild said progress in the first two years of main works was too slow, citing weak design maturity and consenting. The Transport Secretary confirmed that HS2 services would not start by 2033.[3]

Going deeperThe five branchesFive planned pieces, each built to train one assessment objective.

Everything above is the topic page. The pieces below take it further. Each one trains a particular assessment objective rather than covering the topic again, and they are added over the year.

Trains AO2
Branch 01 · The Case
The Case: what the Elizabeth line's late opening shows about dependencies
A real project taken apart, linking late activities and critical-path thinking to the cost of delay.
Planned · Jan 2027
Trains AO1 · AO3
Branch 02 · The Model
The Model: a network from table to critical path
A step-by-step forward pass, backward pass and float calculation, with a check that the answers agree.
Planned · Feb 2027
Trains AO1 · AO3
Branch 03 · The Misconception
The Misconception: float means the task can be left alone
Why non-critical does not mean unimportant, and how float can be used up.
Planned · Mar 2027
Trains AO4
Branch 04 · The Examiner's Line
The Examiner's Line: from a critical path to a judgement
The sentence that turns a calculated critical path into a recommendation based on cost, time and risk.
Planned · Apr 2027
Trains AO1–AO4
Branch 05 · The Question
The Question: a 15-mark project decision at two grades
One practice question answered at two grades, with the differences in application and judgement explained.
Planned · May 2027
ReferencesSourcesEvery figure and fact on this page, with links.
  1. [0]AQA (2025). AS and A-level Business specification 7137/7138, version 1.1 (November 2025)
  2. [1]Gulf News (Reuters photo report) (2022). Photo: London's Elizabeth line rail link finally opens
  3. [2]New Civil Engineer (2024). Hinkley Point C costs rise to £34bn amidst civil engineering price hikes and delayed electromechanical phase
  4. [3]New Civil Engineer (2025). HS2: Just over half of civils completed despite being billions over budget, says chief exec

Figures and facts were checked against these sources on 2 November 2026. Worked numbers labelled "Illustrative figures" are invented for teaching.